Users.
The operation was finished without any troubles.
The installation of the system for preventing the network in Inamori Center from the instantaneous power interruption will be carried out.
- [Date]: March 6, 2012 (Tuesday) 16:00 — 19:00 (network suspension for 5 minutes will be carried out 2 times)
- [Place]: Inamori Center
- [Influence Area]: Network of the following 6 departments in Kyoto University.
- Center for Southeast Asian Studies (CSEAS)
- Graduate School of Asian and African Area Studies (ASAFAS)
- Center for Integrated Area Studies (CIAS)
- The Center for African Area Studies (AFRICA)
- KOKORO Research Center (KOKORO)
- Kyoto University Museum (MUSEUM)
- [Organizer]: Committee of Information infrastructure management for Inamori Center (coordinator: Kitani)
- [Summary of Operations]
The UPS for the network switch will be installed at the following schedule.- 14:00 — 16:00: Preparation of UPS
- 16:00 — 17:00: 3F (Common Meeting rooms, ASAFAS, AFRICA)
- 17:00 — 17:30: 2F (CSEAS, CIAS, KOKORO)
- 17:30 — 18:30: 1F (All departments and common administrative office)
1 March, 2012 Committee of Information infrastructure management for Inamori Center: Kitani.