(Done) Tentative Network Suspension in Inamori Center

Users.

The operation was finished without any troubles.

The installation of the  system for preventing the network in Inamori Center from the instantaneous power interruption  will be carried out.

  • [Date]: March 6, 2012 (Tuesday)  16:00 — 19:00 (network suspension for 5 minutes will be carried out 2 times)
  • [Place]: Inamori Center
  • [Influence Area]: Network of the following 6 departments in Kyoto University.
    • Center for Southeast Asian Studies (CSEAS)
    • Graduate School of Asian and African Area Studies (ASAFAS)
    • Center for Integrated Area Studies (CIAS)
    • The Center for African Area Studies (AFRICA)
    • KOKORO Research Center (KOKORO)
    • Kyoto University Museum (MUSEUM)
  • [Organizer]: Committee of Information infrastructure management  for Inamori Center (coordinator: Kitani)
  • [Summary of Operations]
     The UPS for the network switch will be installed at the following schedule.
    1. 14:00 — 16:00:  Preparation of UPS
    2. 16:00 — 17:00:  3F (Common Meeting rooms,  ASAFAS, AFRICA)
    3. 17:00 — 17:30:  2F (CSEAS, CIAS, KOKORO)
    4. 17:30 — 18:30:  1F (All departments and common administrative office)

 

1 March, 2012  Committee of Information infrastructure management for Inamori Center: Kitani.